A SENIOR manager in charge of the construction of the Glen Sannox ferry has been removed and a further delay to delivery is expected.
Ferguson shipyard said programme director Andy Crossan, who was seconded from Scottish Government ferries agency CMAL, was no longer working on the project.
The CalMac vessel, the first liquefied natural gas (LNG) powered ferry built in the UK, is due for delivery by July 31.
READ MORE: Keir Starmer gives blunt 'no' to independence talks if SNP win majority
Glen Sannox and its sister vessel Glen Rosa were originally due six years ago but have faced repeated delays.
CMAL has blamed "catastrophic" contractor failure - but former yard owner Jim McColl, who rescued it from administration in 2014, claims a flawed specification and subsequent interference by CMAL were the problem.
Crossan joined CMAL as projects director and technical manager in 2015, just a few weeks before the contract was awarded to the Port Glasgow yard.
As the build ran into trouble, relations with McColl's management team became so fraught that he was temporarily banned from the shipyard.
However, in March 2022 he was seconded into the senior leadership team of the now-nationalised shipyard by new boss David Tydeman in a bid to improve the working relationship with CMAL.
Crossan was well-known to many of the workers, having been a manager there from 1990-2007 when the firm was known as Ferguson Shipbuilders.
READ MORE: I just met Keir Starmer and asked if he's a serial liar
A spokesperson for Ferguson Marine said: "We can confirm the secondment arrangement with CMAL has ended and the secondee is no longer supporting the vessels programme."
Final work on Glen Sannox is being carried out a short distance from the Port Glasgow yard, at the Inchgreen quayside in Greenock.
Initial sea trials using traditional marine diesel are said to have gone well, but the dual-fuel ship's LNG systems have yet to be commissioned.
The ship is due to become the main ferry on the busy Arran route but will require several weeks of sea trials by CalMac after delivery before it can carry passengers.
Ferguson said an update on the ship's delivery would be given at the end of this month.
Why are you making commenting on The National only available to subscribers?
We know there are thousands of National readers who want to debate, argue and go back and forth in the comments section of our stories. We’ve got the most informed readers in Scotland, asking each other the big questions about the future of our country.
Unfortunately, though, these important debates are being spoiled by a vocal minority of trolls who aren’t really interested in the issues, try to derail the conversations, register under fake names, and post vile abuse.
So that’s why we’ve decided to make the ability to comment only available to our paying subscribers. That way, all the trolls who post abuse on our website will have to pay if they want to join the debate – and risk a permanent ban from the account that they subscribe with.
The conversation will go back to what it should be about – people who care passionately about the issues, but disagree constructively on what we should do about them. Let’s get that debate started!
Callum Baird, Editor of The National
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules hereLast Updated:
Report this comment Cancel