FERRY operator CalMac has announced that one of its vessels could be out of action until March, causing further disruption to its winter sailing schedule.
MV Caledonian Isles, which is one of the largest vessels in the fleet connecting the Scottish mainland and islands and has been out of action for almost a year, was due to be back on the water by November 20 following planned repairs.
However, that timetable has now been pushed back after the company found further repairs are needed to the ferry’s stern tube bearings, and to sections of steelwork in two areas of the vessel.
The ferry operator said it is not yet known how long the additional work will take to complete, but due to uncertainty around drydock availability and around the full scope of the repairs, it could be late March before the Caledonian Isles is back in service.
READ MORE: Knoydart Foundation gains planning permission for affordable housing
CalMac interim chief executive Duncan Mackison said: “The planned scope of work we’d identified for drydock is progressing well, but the discovery of these latest issues has eliminated any chance of a return to service in the short-term.
“We are in no doubt about the current challenges facing the network and the people who rely on it.
“We anticipated a challenging winter, and that is exactly what we’re seeing play out.
“Any decisions we take around the service off the back of this news will cause disruption in places, and we will now consult with communities to get their valuable input into that service plan.
“Our recent efforts to add resilience to the service, such as through trialling third-party vessels and by bringing forward the drydock work for MV Caledonian Isles, will continue.
“We will leave no stone unturned as we try to meet the needs of the island communities we serve.”
The ferry operator said if new bearings are needed, it could take until mid-December for the first one to arrive.
READ MORE: Images show first look inside Scotland’s first inland surf destination
It also said it is consulting a naval architect on the root cause of the steelwork deformation issue, and is liaising with the drydock operator and other parties on the repair timeline and cost.
CalMac said it will consult island communities this week on a revised vessel deployment plan for winter.
The operator’s current winter plan, which was announced in October, redeploys ferries across the CalMac network to meet demand.
It had been announced on the back of disruption caused by the repairs to MV Caledonian Isles, as well as annual maintenance to a number of other vessels.
Why are you making commenting on The National only available to subscribers?
We know there are thousands of National readers who want to debate, argue and go back and forth in the comments section of our stories. We’ve got the most informed readers in Scotland, asking each other the big questions about the future of our country.
Unfortunately, though, these important debates are being spoiled by a vocal minority of trolls who aren’t really interested in the issues, try to derail the conversations, register under fake names, and post vile abuse.
So that’s why we’ve decided to make the ability to comment only available to our paying subscribers. That way, all the trolls who post abuse on our website will have to pay if they want to join the debate – and risk a permanent ban from the account that they subscribe with.
The conversation will go back to what it should be about – people who care passionately about the issues, but disagree constructively on what we should do about them. Let’s get that debate started!
Callum Baird, Editor of The National
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules hereLast Updated:
Report this comment Cancel